The Ministry in Charge of Emergency Management reviewed progress at Muvumba Dam in Nyagatare District on Thursday, November 19. The Rwanda Water Resources Board reported that construction was 74% complete, about four months before the March 2027 target.
Construction stood at 61.5% in June after heavy rains slowed work. In July, the board said it had worked with the contractor to bring in more workers and equipment to make up for lost time.
During Thursday’s visit to the site in Karama Sector, Minister Albert Murasira asked the project team to identify risks early.
Flooding along the Muvumba River has damaged rice crops and parts of Nyagatare town.
François Xavier Ndekezi, a water resources engineer on the project, said families living near the reservoir had been moved more than 50 metres from its edge to protect them when water levels rise. Crews are planting trees along the banks and plan to terrace the hills above the river to limit erosion.
Thacien Rwampozeho, a cattle farmer in Nyagatare, recalled in January that he used to travel for up to four hours during dry spells to find water for his cows. “What we really need is an expansion of the Muvumba project,” he said.
The dam is designed to supply water for about 10,000 hectares of farmland. The project is also expected to provide 50 million litres of drinking water a day and generate one megawatt of electricity.